Update on Organics Facility

March 17, 2011

Blog, Healthy Environment

As of the end of February 2011 $16,514,235.11 has been spent on this project. This is 50.3% of the total project budget.

To the end of February, 60% of the actual construction has been completed.

Major Construction Activities that occurred during February were:

  • Removal of the south panels of the old maturation hall and commencement of tie-in of pre-engineered segments
  • Completion of installation of pre-engineered building roof deck
  • Continuing to install corrugated metal siding in administration area
  • Backfilled Blower room with granular B and compacted
  • Biofilter media installation for Biofilter Cell #2 and #3 completed
  • Beam and hollow core slab installation completed for biofilter.

Click here to view recent photos which will show you that construction is progressing quickly.

About Karen Farbridge

An unwavering change maker seeking a just, democratic and sustainable world.

View all posts by Karen Farbridge

Connect with the City of Guelph

Subscribe to our RSS feed and social profiles to receive updates.

Comments are closed.

%d bloggers like this: